Week of: August 27, 2001 – August 31, 2001

Work Accomplished:

Safety Update:

  • Conducted daily safety inspections on all heavy equipment used on site.
  • All work was completed in level D personal protective equipment.

Work Accomplished by WESTON and Subcontractors:

  • Continued contaminated soil screening operation.
  • Continued Area 1 and Area 4 excavation.
  • Continued demolition of mill building foundation in Area 1.
  • Completed removal of Main Street bridge in front of former mill building.
  • Water treatment plant operated for 5 days.
  • Continued site dust control.

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (September 3 through September 17).

  • Continue Area 1 excavation.
  • Complete Area 4 excavation.
  • Begin Mill Pond Restoration.

 


 