Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.

August 19, 2000

 

Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.

 

PUBLIC WEEKLY UPDATE #8

EASTLAND WOOLEN MILL SITE

CORINNA, ME

 

The following summarizes WESTON's work completed on the Eastland Woolen Mill Site ( for week ending Saturday August 19, 2000:

 

Safety Update:

  • Conducted daily safety inspections on the heavy equipment used on site.
  • Performed real-time air monitoring of the site perimeter.
  • Workers in excavation area continued to wear modified level D personal protective equipment.

 

Work Accomplished:

  • Completed excavation of Area 3. Excavated approximately 6000 yd3 of contaminated soil from the river (Area 3).
  • Stockpiled all excavated contaminated soil at the designated soil stockpile area on-site.
  • Continued excavation of clean river bank material from Area 3 in order to access deeper soils. Excavated a total of 1215 yd3 of clean riverbank material from Area 3.
  • Continued backfilling of Area 3 with clean soil.
  • Collected daily soil samples from the excavation area and sent to the on-site laboratory for analysis.
  • Continued work on improving the layout of the water treatment system.
  • Performed daily water quality readings for turbidity, temperature and dissolved oxygen at locations near Corundel Lake dam and downstream of the Area 3 excavation.
  • Continued installation of water line from Rt. 222 towards the river. Also installed approximately 200’ of sewer line along Rt. 222.
  • Performed a topographical survey of Area 2.
  • Continued dust control around the work site.
  • Continued night shift monitoring of pumps.

 

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (August 21 through September 4):

  • Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
  • Continue maintenance of dewatering pumps, river bypass pumps, and all associated piping.
  • Continue backfilling of Area 3.
  • Continue excavation and removal of clean bank material from Area 2.
  • Complete demolition of buildings on Main Street and Rt. 7 & 11.
  • Preparatory work for moving Odd Fellows building.
  • Continue dust control and air monitoring.
  • Continue utility relocation along Stetson and Newport Roads.
  • Begin excavation in Area 2 (north of railroad trestle).

 


 

The Cattail Press Homepage