The following summarizes WESTON's work completed on the Eastland Woolen Mill Site (Task Order 0001) for week ending Friday August 10, 2001:

Safety Update:

  • Conducted daily safety inspections on the heavy equipment used on site.
  • Workers around the work areas wore level D personal protective equipment.

Work Accomplished by WESTON and Subcontractor:

  • Screened soil and moved from old stockpile to new stockpile.
  • Excavated in Area 4 Pump House Area using shoring system.
  • Finished excavation in Building 1A area.
  • Did not operate water treatment plant.
  • Continued site dust control.

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (August 13 through August 24):

  • Complete Area 4 Pump House excavation.
  • Begin Area 1 excavation.
  • Remove old bridge
  • Continue river diversion

 


 