Weekly Update
from Roy F. Weston, Inc.

 

August 24, 2001

Karen Campbell of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.

PUBLIC WEEKLY UPDATE

NON-TIME CRITICAL REMOVAL ACTION

EASTLAND WOOLEN MILL SITE

CORINNA, ME

 

The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday August 24, 2001:

Safety Update:

  • Conducted daily safety inspections on the heavy equipment used on site.
  • Workers around the work areas wore level C and D personal protective equipment.


Work Accomplished by WESTON and Subcontractor:

  • Screened soil and moved from old stockpile to new stockpile.
  • Continued demolishing Mill foundation.
  • Continued Area 1 excavation.
  • Water treatment plant operated for five days.
  • Continued site dust control.

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (September 4 through September 14):

  • Repair Corundel Lake Dam.
  • Continue Area 1 excavation.

 


 