Work Accomplished:
Safety Update:
- Conducted daily safety inspections on all heavy equipment used on site.
- All work was completed in level D personal protective equipment.
Work Accomplished by WESTON and Subcontractors:
- Continued contaminated soil screening operation.
- Continued Area 1 and Area 4 excavation.
- Continued demolition of mill building foundation in Area 1.
- Completed removal of Main Street bridge in front of former mill building.
- Water treatment plant operated for 5 days.
- Continued site dust control.
Two-week Projection:
The following summarizes the anticipated work to be completed for the next two week time period (September 3 through September 17).
- Continue Area 1 excavation.
- Complete Area 4 excavation.
- Begin Mill Pond Restoration.