Weekly Update
from Roy F. Weston, Inc.
January 12, 2001
Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
PUBLIC WEEKLY UPDATE
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday January 12, 2000:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Workers around the work areas continued to wear level D personal protective equipment.
Work Accomplished by WESTON and Subcontractor:
Subcontractor oversight. Performed snowmobile trail maintenance. Continued snow removal and general housekeeping around the site. Prepared north wing wall on abutment #1 for pour on 1/12/01. Completed 12yd3 pour of north wing wall on abutment #1. Completed pour of Odd Fellows basement. Began installation of electrical boxes/cables in Odd Fellows Building. Began saw-cutting Odd Fellows basement slab.
Two-week Projection:
The following summarizes the anticipated work to be completed for the next two week time period (January 15 through January 29):
- Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
- Continue bridge construction.
- Complete installation of electricity and other utilities in Odd Fellows Building.
- Monitor winter cover on contaminated soil stockpile.