Weekly Update
from Roy F. Weston, Inc.
January 19, 2001
Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
WEEKLY PUBLIC UPDATE
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday January 19, 2000:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Workers around the work areas continued to wear level D personal protective equipment.
Work Accomplished by WESTON:
Subcontractor oversight. Re-route snowmobile trail to east side of pump house. Continued snow removal and general housekeeping around the site. Completed saw-cutting Odd Fellows basement slab. Completed installing anchors between sill and Odd Fellows basement walls. Cleaned bridge abutment form-work and sent off-site. Began to construct and install deck shoring. Continue installation of electrical connections in Odd Fellows basement. Completed construction of interior stairs from Odd Fellows basement to first floor. Began construction of retaining wall for outside stairwell to Odd Fellows basement.
Two-week Projection:
The following summarizes the anticipated work to be completed for the next two week time period (January 22 through February 5):
- Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
- Continue bridge construction.
- Complete installation of electricity and other utilities in Odd Fellows Building.
- Complete construction of outside stairwell.
- Monitor winter cover on contaminated soil stockpile.