Weekly Update
from Roy F. Weston, Inc.
August 3, 2001
Karen Campbell of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
PUBLIC WEEKLY UPDATE
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site (Task Order 0001) for week ending Friday August 3, 2001:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Workers around the work areas wore level B, C and D personal protective equipment.
Work Accomplished by WESTON and Subcontractor:
Screened soil and moved from old stockpile to new stockpile. Excavated Cells in Area 4 Pump House Area using shoring system Completed road and bridge. Began excavation of Building 1A Area. Continued site dust control.
Two-week Projection:The following summarizes the anticipated work to be completed for the next two week time period (August 6 through August 17):
- Complete Area 4 Pump House excavation.
- Complete excavation of Building 1A Area.
- Demolish Mill Foundations.
- Begin Area 1 excavation.
- Continue river diversion.