Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.
October 27, 2000
Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
PUBLIC WEEKLY UPDATE
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday October 27, 2000:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Conducted daily air monitoring along the perimeter of Area 4. Preliminary analytical results for samples were below detection limits.
- Conducted daily real-time air monitoring for the perimeter of the former mill property and the exclusion zone. Results were below the action levels.
- Workers in excavation areas continued to wear modified level D personal protective equipment.
Work Accomplished by WESTON:
Backfilled approximately 945yd3 of gravel material in Areas 2, 2.5, and 3 south. Installed approximately 182 yd3 of rocks/stones in Area 3 south. Transported 588yd3 of contaminated material from Area 4 stockpile to main contaminated soil stockpile Performed water quality readings (temperature, DO, turbidity) above Corundel dam and downstream of Area 3 excavation. Collected a total of 62 soil samples from Building 9 area. Surveyed all soil sample collection location, and continued surveying riverbed location. Completed installation of box culverts. Installed dry hydrant on Adler Stream off Rt. 222. Continued contaminated soil stockpile maintenance. Moved Odd Fellows Building onto new foundation on Rt. 222. Continued work on new Odd Fellows Building foundation. Continued dust control around the work site. Continued night shift monitoring of pumps.
Two-week Projection:
The following summarizes the anticipated work to be completed for the next two week time period (November 6 through November 20):
- Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
- Continue maintenance of dewatering pumps, river bypass pumps, and all associated piping.
- Continue backfilling of box culverts.
- Continue lining sides of riverbed with stones/rocks.
- Continue Building 14 excavation.
- Continue bridge and road work.
- Place winter cover on contaminated soil stockpile.
- Pour Odd Fellows Building foundation walls.
- Continue dust control and air monitoring.