Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.
November 3, 2000
Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
WEEKLY PUBLIC UPDATE
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday November 3, 2000:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Conducted daily air monitoring along the work areas (Area 4 and bridge excavation area). Preliminary analytical results for samples were below detection limits.
- Workers in around the work areas continued to wear level D personal protective equipment.
Work Accomplished by WESTON:
Backfilled an additional 3033yd3 of material in Areas 2 and 2.5 around box culverts. Continued the riverbed restoration by placing approximately 422yd3 of rocks and boulders in Areas 2.5 and 3 south. Began preparation for Building 14 work. Continued surveying location of new riverbed. Began disassembling 12", 8" and 4" pipe from within the former Odd Fellows Building foundation. Continued work on the new Odd Fellows Building foundation. Began sheet piling installation at the Main Street bridge excavation. Continued contaminated soil stockpile maintenance. Continued dust control around the work site. Continued night shift monitoring of pumps.
Two-week Projection:
The following summarizes the anticipated work to be completed for the next two week time period (November 13 through November 27):
- Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
- Continue maintenance of dewatering pumps, river bypass pumps, and all associated piping.
- Continue backfilling of box culverts.
- Continue lining sides of riverbed with stones/rocks.
- Complete Building 14 work.
- Continue bridge and road work.
- Place winter cover on contaminated soil stockpile.
- Complete Odd Fellows Building foundation work.
- Continue dust control and air monitoring