Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.

November 10, 2000

 

Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.

 

PUBLIC WEEKLY UPDATE

NON-TIME CRITICAL REMOVAL ACTION

EASTLAND WOOLEN MILL SITE

CORINNA, ME

 

The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday November 10, 2000:

Safety Update:

  • Conducted daily safety inspections on the heavy equipment used on site.
  • Conducted daily air monitoring along the work areas (Area 4 and bridge excavation area). Preliminary analytical results for samples were below detection limits.
  • Workers in around the work areas continued to wear level D personal protective equipment.

 

Work Accomplished by WESTON:

  • Backfilled 1230 yd3 of native material around box culverts in Areas 2 and 2.5.
  • Installed an additional 105 yd3 of rocks/stones along the new riverbed.
  • Constructed and installed carbon trench south of the former Odd Fellows Building foundation.
  • Excavated and sampled 3 test trenches (4’ wide x 20’ long x 14’ deep) at Building 14.
  • Began 12", 8" and 4" pipe consolidation.
  • Collected 63 soil samples from Building 14 test trenches, 13 soil samples from bridge abutment excavation area, and 24 soil samples from the bridge abutment excavation soil stockpiles.
  • Surveyed soil sample collection locations in Building 14.
  • Began installation of fence along the north side of the detour road.
  • Continued contaminated soil stockpile maintenance.
  • Continued work on Odd Fellows Building new foundation.
  • Completed sheet piling installation at the Main Street bridge excavation.
  • Re-paved section of the Main Street detour road.

 

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (November 13 through November 27):

  • Divert river through box culverts.
  • Return piping and pumps no longer necessary for river diversion pumping.
  • Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
  • Complete backfilling of box culverts.
  • Complete riverbed restoration.
  • Continue bridge and road work. Pour footings for bridge abutments.
  • Place winter cover on contaminated soil stockpile.
  • Pour new foundation walls for Odd Fellows Building.
  • Continue dust control and air monitoring of the site.

 


 