Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.
September 22, 2000
Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.
PUBLIC UPDATE #13
NON-TIME CRITICAL REMOVAL ACTION
EASTLAND WOOLEN MILL SITE
CORINNA, ME
The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday September 22, 2000:
Safety Update:
- Conducted daily safety inspections on the heavy equipment used on site.
- Conducted daily air monitoring along the perimeter of the mill complex fencing including Areas 2 & 3, the stockpile area, and the decontamination pad. Preliminary analytical results for samples were below detection limits.
- Conducted daily real-time air monitoring for the perimeter of the former mill property and the exclusion zone. Results were below the action levels.
- Workers in excavation areas continued to wear modified level D personal protective equipment.
Work Accomplished by WESTON:
Began excavation of Area 2. Excavated a total of 2730 yd3 of contaminated material from Area 2. Began backfilling Area 2.5 with gravel. Backfilled approximately 1187yd3 into Area 2.5. Backfilled 648yd3 of material into Area 2 behind the Odd Fellows Building. Continued dewatering activities in Area 2.5. Continued preparation for stockpile extension, and began installation of 40-mil LLDPE liner. Placed frac tank in Lot #88. Continued dewatering activities in Area 2.5. Performed water quality readings (temperature, DO, turbidity) above Corundel dam and downstream of Area 3 excavation. Collected 41 soil samples from Area 2 and 2.5, and surveyed all soil sample collection locations. Completed installation of water line. Continued installation of sewer line along Rt. 222 and Rt. 7/11. Continued preparation for Odd Fellows Building move by removing non-load bearing basement walls, and installing tension wires. Continued dust control around the work site. Continued night shift monitoring of pumps.
The following summarizes the anticipated work to be completed for the next two week time period (October 2 through October 16):
- Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
- Continue maintenance of dewatering pumps, river bypass pumps, and all associated piping.
- Complete backfilling of Area 2 and 2.5.
- Complete extension of contaminated soil stockpile area.
- Continue excavation and removal of clean bank material from Areas 2.
- Pour foundation for Odd Fellows building on Lot 118A.
- Continue Odd Fellows Building move preparation.
- Continue dust control and air monitoring.
- Complete utility relocation along Stetson and Newport Roads.
- Remove traffic detour for utility installation on Newport Road.